Skip to content
a group of men on a crane

Analyzing Your Construction Organization’s Project Progress Using the Schedule Performance Index and Cost Performance Index

Published
Oct 9, 2024
Share

Job costing and budgeting are critical to the profitability and success of all construction projects. The cost performance index (CPI) and schedule performance index (SPI) are useful tools to help assess a project's efficiency, cost, and schedule performance so your organization can better track, manage, and control the execution of your construction projects.  

What Is the Schedule Performance Index? 

The schedule performance index measures a project’s progress and whether it’s ahead of or behind schedule. The SPI is calculated by dividing a project’s earned value (the amount of work completed) by the planned value (the budgeted cost of work scheduled). Below are two examples illustrating this calculation:   

Example 1 | Schedule Performance Index =
Earned Value /
Planned Value 

Project Value

SPI

  

EV-PV %

Value

Budget 

  

  

  

 $450,000  

Earned Value (EV): % of work completed * budget 

  

  

40% 

 $180,000  

Planned Value (PV): % planned completion * budget 

  

  

50% 

 $225,000  

Actual Cost (AC): Funds spent up to the measured point 

  

  

  

 $225,000  

  

SPI < 1 = 

EV 

Divided By 

PV 

Less than one signifies that the project is behind schedule 

0.8 

 $180,000  

  

 $225,000  

 

Example 2 | Schedule Performance Index =
Earned Value /
Planned Value

Project Value 

SPI

 

EV-PV %

Value

Budget 

  

  

  

 $450,000  

Earned Value (EV): % of work completed * budget 

  

  

40% 

 $180,000  

Planned Value (PV) % planned completion * budget 

  

  

20% 

 $90,000  

Actual Cost (AC): Funds spent up to the measured point 

  

  

  

 $225,000  

  

SPI > 1 = 

EV 

Divided By 

PV 

Greater than one signifies that the project is ahead of schedule 

2

 $180,000

  

 $90,000  

 

If the SPI is more than one, the project is ahead of schedule. If the SPI is less than one, the project is behind schedule. Investigate to determine the root cause for the negative SPI, so you can effectively plan for and mitigate any potential delays in reaching project commitments. 

What Is the Cost Performance Index? 

The cost performance index measures the financial performance of a project and whether it’s on budget. The CPI is equal to the budgeted cost of work performed divided by the actual cost of work performed. Below are two examples illustrating this calculation:   

Example 1 | Cost Performance Index =
Earned Value /
Actual Cost 

Project Value 

CPI 

  

EV-PV % 

Value 

Budget 

  

  

  

 $450,000  

Earned Value (EV): % of work completed * budget 

  

  

40% 

 $180,000

Planned Value (PV): % planned completion * budget 

  

  

50% 

 $225,000

Actual Cost (AC): Funds spent up to the measured point  

  

  

  

 $200,000

  

CPI < 1 = 

EV 

Divided By 

AC 

Less than one signifies that the project is over the budget of planned resources at the time of the measurement 

.90 

 $180,000

  

 $200,000 

 

Example 2 | Cost Performance Index =
Earned Value /
Actual Cost

Project Value 

CPI 

  

EV-PV % 

Value 

Budget 

  

  

  

 $450,000  

Earned Value (EV) %of the work completed * budget 

  

  

40% 

 $180,000  

Planned Value (PV) % planned completion * the budget 

  

  

20% 

 $90,000  

Actual Cost (AC) money spent up to the measured point 

  

  

  

 $160,000  

  

CPI > 1 = 

EV 

Divided By 

AC 

Greater than one signifies that the project is within the budget of planned resources at the time of the measurement 

1.125

 $180,000

 

 $160,000

  

If the CPI is greater than one, the project is within budget; if the CPI is less than one, the project is over budget. Construction organizations should regularly compare the CPI estimates to identify potential schedule variances and cost overruns. 

Ideal Target Levels for the Cost and Schedule Performance Indexes 

The target values of the cost and schedule performance indexes should be within one standard deviation from the expected values for both indices. If either index is above or below one standard deviation from the expected projections, investigate any potential errors in the calculation, data used, or substantial project risks. 

Using the CPI and SPI for Assessing Project Performance 

While the CPI and SPI are valuable for assessing overall project performance, they don’t pinpoint specific areas for improvement or identify trouble spots. Regularly reviewing the CPI, SPI, and other financial statement ratios can help you recognize problems and identify weaknesses, so you can adjust scheduling and budgets accordingly and gain deeper insights into your project’s financial health.  

What's on Your Mind?

a man in a suit smiling

Craig Mann

Craig Mann is a Senior Manager in the Forensic, Litigation & Valuation Group with extensive experience in construction progress billing and accounting for large-scale projects.


Start a conversation with Craig

Receive the latest business insights, analysis, and perspectives from EisnerAmper professionals.